1216 MW Khimti Those Siwalaya & 110 MW Kokhajor Storage Hydro Project 

Brief Scope of Works : Details surveys investigations and preparation of Feasibility Study and Environmental Impact Assessment (EIA) Study Report.

Name of Client : Departments of Electricity Development (DOED) Under ministry of Energy, Water Resources and Irrigation Government of Nepal.

Location of Project : Nepal

Commencement Date : March 2020

130 MW Kandadji Hydroelectric Dam Project, Niger 

Project : KANDADJI ECOSYSTEM REGENERATION AND NIGER VALLEY ENHANCEMENT PROGRAM.

Name of Client : KANDADJI DAM AGENCY (ABK), Niger

Duration Of Contract : 72 Months

About the Project :

Kandadji Hydroelectric Dam is an important elementof the Kandadji Ecosystem Regeneration and Development Program of the Niger Valley.

The dam will be used for the production of energy of 130 MW by the 4 groups, protection against floods and irrigation.

Most of the dam will be earth and of the homogeneous backfill type, 8.4 Km long and a maximum height of 26m. 

Services Provided by EIPL :

EIPL shall provide following consultancy services for the project :

  • Mission 1: Preparation of Detailed Project Report / Engineering Report.
  • Mission 2: Implementation Plans.
  • Mission 3: Supervision of works and provisional acceptance.
  • Mission 4: Monitoring of the implementation of Environmental Management Plans and Social work sites developed by companies
  • Mission 5: Assistance to the Contracting Authority.
  • i) Assistance provided during the warranty period
  • ii) Assistance offered to the Owner for Operation and Maintenance.
  • iii) Technology Transfer and training of the Client's staff
Hale Rehabilitation 21 MW,Tanzania

Brief Scope of Works : Consultancy services for Hale Hydropower Plant Rehabilitation Project, Tanzania

Name of Client : Tanzania Electric Supply Company Limited (TANESCO)

Location of Project : Tanzania

Duration Of Contract : June 2015 – June 2020

About the Project :

The Government of Tanzania through TANESCO has decided to rehabilitate Hale hydropower plant in Tanga Region. Presently the power plant is suffering from general aging and wear and tear. One generator is completely down and the rest of the plant is in obsolete condition. The Government intends to have the station rehabilitated back to its full capacity of 21 MW.

The project shall be carried out in accordance the following documents :

  • Rehabilitation of Hale Hydropower Plant in Tanga Region, Tanzania, Final Project Document, 4 December 2007 (PD 2007)
  • Rehabilitation of Hale Hydropower Plant in Tanga Region, Tanzania, Final Feasibility Study Report, 7 December 2007 (FS 2007)
  • Rehabilitation of Hale Hydropower, UPDATE of Final Feasibility Study Report, 8 November 2010 (FS 2010 Update)

Services Provided by EIPL :

In association with SWECO, Sweden, EIPL has been appointed as Client’s Engineer by TANESCO for providing consultancy services for rehabilitation of Hale Hydropower Plant on Pangani River. The Contract Agreement has been signed by SWECO & EIPL.

EIPL’s scope of work includes :

  • Update the Existing feasibility report for Rehabilitation of Hale Hydropower Plant
  • Prepare Tender Documents and provide assistance in evaluation and selection of EPC contractors
  • All works related to civil structures of the project including all investigations, testings Review of Designs, Project Management, contract administration.
  • Supervision of rehabilitation/construction of civil structures, Construction as Client’s Engineer at site.
44MW Singrobo - Ahouaty Hydropower Project, Ivorie Cote, Africa

Brief Scope of Works : Owner's Engineers for Review of Designs, Factory Inspections, Quality Assurance, Site Supervision and Commissioning of 44 MW Singrobo - Ahouaty Hydropower Project, Ivorie Cote.

Name of Client :Ivorie Hydro Energy SA (IHE), Africa

Location of Project :Ivorie Cote

Commencement Date : Jan 2019


Water Sustainability Study & Design
  • Water Intake system Raipur USTPP 

    Brief Scope of Works : 

  • Study of Water Availability & Intake for Raipur USTPP
  • Detailed Expansion Project
  • Design of Intake
  • Name of Client :  Adani Power Limited

    Location of Project :  Chhattisgarh

    Commencement Date :   08-02-2024


  • Water Intake System Kawai USTPP 

    Brief Scope of Works : 

  • Study of Water Availability & Intake for Kawai USTPP
  • Detailed Expansion Project
  • Design of Intake
  • Name of Client :  Adani Power Limited

    Location of Project :  Rajisthan

    Commencement Date :  22-03-2024


  • Raigarh USTPP 

    Brief Scope of Works : 

  • Water Availability Study for Raigarh USTPP
  • Detailed Expansion Project
  • Name of Client :  Adani Power Limited

    Location of Project :  Chhattishgarh

    Commencement Date :  12-02-2024


Pre - Feasibilty Studies of Pumped Storage of PSP Project in Gujarat - GSECL

    Brief Scope of Works :  Preparation of Pre feasibility Report of 35 Pump Storage Power Project

    Name of Client :  GSECL

    p>Location of Project :  Gujarat

    Commencement Date :   26-03-2024


PFR of Pumped Storage Project in Maharashtra & Uttarakhand

    Brief Scope of Works : Site Identification & preparation of Pre Feasibility report of PSP Project

    Name of Client :  JSW

    Location of Project : Maharashtra & Uttrakhand

    Commencement Date :   17-01-2024


PFR Study of Pumped Storage Project in Tamil Nadu & Telangana
  • Tamil Nadu:

    Brief Scope of Works :  Preparation of Pre Feasibility report of PSP Project

    Name of Client : Adani Power Limited

    Location of Project : Alleri & Thenamalai

    Commencement Date :  March 2024


  • Telangana:

    Brief Scope of Works : Preparation of Pre Feasibility report of PSP Project

    Name of Client : Adani Power Limited

    Location of Project : Nacharam & Koyabestagudem

    Commencement Date :  March 2024


Lender's Engineer Assignments for PFC & REC

    Projects: 120 MW Rangit-IV Hydro-electric Project in Sikkim, 96MW Rongnichu Hydro-electric Project in Sikkim, 24 MW Selti Musrang Hydroelectric Project in Himachal Pradesh, Project Management Services for 18 MW Saptdhara Hydroelectric Project, Orissa

    Brief Scope of Works :EIPL provides following consultancy services for execution of Lender’s Engineering services.

    Name of Client : Power Finance Corporation & Rural Electrification Corporation

    Services Provided by EIPL :

    Power Finance Corporation & Rural Electrification Corporation has appointed M/s Energy Infratech Private Limited (EIPL) as Lender Engineers (LE) for providing consultancy services for financing of various Projects.

    PHASE I : DUE DILIGENCE(Pre-Financial closure):

    Critical Review of Project System Design and agreements covering: Conceptual Design, Power Purchase agreement, Turnkey/ packages/Sub package contracts including non EPC items for engineering procurement, construction, start up, Hydrology and Power potential, Adequacy of Power evacuation arrangements, Infrastructure availability and adequacy, Environmental issues, if any, Review and acceptance of Disbursement schedule

    PHASE II : IMPLEMENTATION

    PHASE III : POST COMMISSIONING

Tender Specification of Ruzizi-IV Hydro Power Project

Project : Technical Study for Preparation of Feasibility Study (Detailed Project Report) & Tender Specification of Ruzizi-IV Hydro Power Project

Brief Scope of Works : Preparation of Feasibility Study Report & Tender Specifications

Name of Client : Organisation for the Energy of Great Lakes Countries (EGL)

Location of Project : RAWANDA, BURUNDI & DR CONGO

Lender : AFRICAN DEVELOPMENT BANK (AFDB)

Commencement Date : 18-07-2024


Improvement of Electric Sector of DR CONGO (PAGASE)

Project : Construction Supervision of Improvement of Electric Sector of DR CONGO (PAGASE)

Scope of Works :

  1. Engineering Review
  2. Construction Supervision of rehabilitation of Inga Hydro Poer Project & Exanpansion of Lungudi Hydro Power Project.
  3. Refurishment of Electrical Transmission & Distribution System

Name of Client : Ministry of Hydraulic & Electricity Resources

Location of Project : RAWANDA, BURUNDI & DR CONGO

Lender : AFRICAN DEVELOPMENT BANK (AFDB)

Commencement Date : 29-04-2024


Upper Bhavani Pumped Storage Project(4X250MW), Tamil Nadu

Project : Preparation of Detailed Project Report (DPR) of Upper Bhavani Pumped Storage Project (4X250MW), TamilNadu

Scope of Works : 

  1. Survey of Investigation
  2. Engineering Studies
  3. EIA/EMP Studies Including MOEF'S Clearance
  4. Economic & Financial Analysis

Name of Client : NTPC Tamil Nadu Energy Company LTD (NTECL),
AJoint Vendture of NTPC Ltd & TANGEDCO

Location of Project : Nilgris(Tamil Nadu)

Commencement Date : 23-07-2024


DPR of 9 Pumped Storage Hydropower Projects at various locations in Gujarat

Project : Preparation of Detailed Project Report for Pumped Storage Hydropower Projects at various locations in the state of Gujarat.

Scope of Works : 

  1. Survey of Investigation
  2. Engineering Studies
  3. EIA/EMP Studies Including MOEF&CC Clearance
  4. Economic & Financial Analysis

Name of Client : Gujarat State Electricity Cooperation Limited

Location of Project : Gujarat

Commencement Date : 15-10-2024